Mount Isa gets new industrial power station

Siemens Ltd

Friday, 05 December, 2014


Mount Isa gets new industrial power station

Siemens has recently completed the commissioning of a power station consisting of two of the most efficient combined cycle power units - performing at well in excess of 50% efficiency. The owner and operator of the plant is Diamantina Power Station, a joint venture between APA Group and AGL Energy.

The Diamantina combined cycle power station in Mount Isa in Queensland has been built adjacent to the existing Mica Creek power station. The installed total capacity of 242 MW is sufficient to supply eco-friendly electricity to local mines operated by Glencore and to people living in the region.

Siemens has been responsible for the overall plant design and also provided technical advisory services during the construction and commissioning phases of the project. The Diamantina Power Station is set out in a configuration of two 121 MW power blocks.

The Siemens scope of supply encompassed two power islands each comprising two SGT-800 gas turbines, two heat-recovery steam generators (HRSGs) with diverter dampers - both supplied by NEM Energy b.v. - as well as one SST-400 steam turbine connected to the local grid via 132 kV electrical switchyard.

Siemens will provide maintenance for the SGT-800 gas turbines, SST-400 steam turbines, generators and the related control and auxiliary systems under a long-term services agreement. “Diamantina power station is a great example of our eco-friendly power generation solutions for island off-grid operation matching the variable power demand of the adjacent copper mine," said Erling Bruun, head of Industrial Power Plant Solutions in Siemens Power and Gas Division.

David Jones, general manager development of the APA Group, comments: “We are very satisfied with the plant and with Siemens' performance. This plant meets the challenging demands of island operation and load flexibility, in combination with bringing a high efficiency and state-of-the-art low emission technology and solutions."

Related Articles

How can we manage our grid workload efficiently and sustainably?

As national demand for electricity continues to grow, there are still questions surrounding our...

How multifaceted tech can help tame Australia's bushfire threat

Following a warmer than expected winter and high fuel loads in many areas, Australian authorities...

Gearboxes for wind-harvesting kite ships

To support production of wind-powered hydrogen, startup OCEANERGY opted to use WITTENSTEIN...


  • All content Copyright © 2024 Westwick-Farrow Pty Ltd