Power usage effectiveness in data centres

B&R Enclosures Pty Ltd
Monday, 20 April, 2009


The Power Usage Effectiveness (PUE) metric is a simple way of measuring the efficiency of data centre power usage, to allow for better understanding of energy consumption. Many organisations use the PUE to make decisions on their infrastructure that relate to power and cooling, how it manages with increased demand as well as reduce the impact of their data centre on the environment.

The PUE metric was created by the Green Grid organisation, a not-for-profit association of professionals aimed at increasing data centre efficiency. This organisation includes such companies as CISCO, Dell, Intel, HP, IBM and Sun. The formula is simply: divide the total facility power by the power used for the IT equipment.

PUE = Total Facility Power/IT Equipment Power

The Total Facility Power can be measured at the utility meter; however, it is important that this figure relates only to the energy used within the data centre. If the data centre is located within an office building, it is important to measure the power used in the data centre separately from the offices. The IT Equipment Power measurement should be the total power distributed to the computing equipment.

The ideal is to get as close as possible to 1.0, which means 100% of a facility’s power is being used for computing. In reality, lighting, cooling, etc will always consume some power which will increase the PUE. If the calculated PUE is 2.0, that means a data centre is using twice the power necessary to run the IT equipment. This is certainly not an uncommon PUE figure.

Having a low PUE has become a key factor in having a competitive data centre with many large organisations focusing on getting lowest PUE possible. Google has achieved an exceptional PUE of 1.19 (measured over a 12-month period) after analysing and adjusting power usage using the PUE metric.

To improve a PUE, organisations may look at modifications to cooling systems, as this can be one of the main influences on energy consumption. Hot/cold aisle arrangements can certainly help, as can an analysis of localised hot spots in the data centre.

The Green Grid website (www.thegreengrid.org) provides a reporting and certification feature which allows for all information relating to the conditions of PUE testing to be published and/or verified depending on level chosen.

B&R Enclosures
www.brenclosures.com.au

Related Articles

Clearing the conduit confusion

One of the greatest concerns to the health and safety of registered cables is a complete...

Benefits of industrial wireless in IP surveillance networks

The benefits of industrial wireless networks in IP surveillance are growing significantly....

Solar 2015

More than 4000 solar enthusiasts are expected to converge on the Melbourne Convention &...


  • All content Copyright © 2024 Westwick-Farrow Pty Ltd